The construction works in the municipality of Sandanski will be performed by the „PUTNO PODDURZHANE“

On January 7, 2021, the Municipality of Sandanski signed a construction contract with "PUTNO PODURZHANE" DZZD, for arranging the riverbed of the river Sandanska Bistrica in the village Liljanovo, municipality of Sandanski within the project CB006.2.12.062 "Joint actions for prevention and reduction of the consequences of disasters in the municipalities of Sandanski and Radovish" funded by the EU, through INTERREG – IPA Cross-Border Cooperation Program between Bulgaria and Republic of North Macedonia, CCI No. 2014TC16I5CB006.

The contract is worth a total of 292,538.51 BGN, and construction and installation activities began on February 26, 2021. So far, 80% of the activities have been carried out, including preventive cleaning of the riverbed at the site of intervention, excavation and relocation of land masses, logs and other vegetation.

For arranging the river bad part of the repair concrete walls were built, as well as rectangular gabions. The construction works on the river Sandanska Bistirica are planned to be completed with afforestation activities.

This project is co-funded by EU through Interreg-IPA CBC Programme Bulgaria - Republic of North Macedonia

This website was created and maintained with the assistance of the European Union through the Interreg-IPA CBC Republic of Bulgaria – Republic of North Macedonia Programme, CCI No 2014TC16I5CB006. The contents of this website are the sole responsibility of the project partners - Centre for development of the South-East planning region and Municipality of Sandanski and can in no way be taken to reflect the views of the European Union or the Managing Authority of the Programme.